Maritime Questions › Permit To Work Rank
As authorising officer, the Chief Officer is under schedule pressure to get hull touch-up work done before a port call, and the only window is while manoeuvring slowly into the anchorage. What should the Chief Officer decide?
A. Wait until the vessel is actually anchored or stopped before authorising the work, even under schedule pressure — the restriction exists specifically for situations where "nearly there" feels close enough but isn't
B. Delegate the decision to the bosun carrying out the work
C. Authorise the work during the final approach, since the vessel is already slowing for anchoring
D. Authorise the work but require an additional safety observer to compensate for the vessel still moving
Sign in or create a free account to see the answer and explanation.
A. There is no fixed maximum — it depends entirely on the job
B. 48 hours, renewable once without re-inspection
C. 24 hours from issue, with any shorter job-specific time limits also stated on the permit
D. 7 days, matching the standard watch rotation
Sign in or create a free account to see the answer and explanation.
A. Accept the outgoing OOW's assessment and take no further action since the job scope hasn't changed
B. Cancel the job immediately without consulting the authorising officer
C. Wait until the 24-hour mark is actually reached before mentioning anything
D. Check elapsed time against the 24-hour limit, recognise it's close to expiry, and flag to the authorising officer that revalidation will be needed rather than letting it lapse unnoticed
Sign in or create a free account to see the answer and explanation.
+36 more Permit To Work Rank questions available
Create a free account to practise all 39 questions, track your accuracy, and build your Reputation Score.
Create Free Account