Maritime Questions › Permit To Work Rank
An OOW taking over the watch finds a permit for overside work was issued 20 hours ago and the job is still running. The outgoing OOW says it's "basically the same job, don't worry about it." What should the new OOW do?
A. Accept the outgoing OOW's assessment and take no further action since the job scope hasn't changed
B. Cancel the job immediately without consulting the authorising officer
C. Wait until the 24-hour mark is actually reached before mentioning anything
D. Check elapsed time against the 24-hour limit, recognise it's close to expiry, and flag to the authorising officer that revalidation will be needed rather than letting it lapse unnoticed
Sign in or create a free account to see the answer and explanation.
A. There is no fixed maximum — it depends entirely on the job
B. 48 hours, renewable once without re-inspection
C. 24 hours from issue, with any shorter job-specific time limits also stated on the permit
D. 7 days, matching the standard watch rotation
Sign in or create a free account to see the answer and explanation.
A. Decline the informal extension, stop the job, and either re-inspect and issue a fresh permit or hold the work until conditions can be properly re-checked
B. Agree to the margin initial since the job is nearly complete and re-inspection would only confirm what's already known
C. Delegate the decision to the contractor's site supervisor
D. Allow the extension but make a note in the deck log for the record
Sign in or create a free account to see the answer and explanation.
+36 more Permit To Work Rank questions available
Create a free account to practise all 39 questions, track your accuracy, and build your Reputation Score.