During an internal audit, the Master discovers a pattern of permits across several months being informally extended past 24 hours by Chief Officers under operational pressure, with no incidents resulting. How should the Master treat this finding?
A. Raise the company's standard validity period to 48 hours to match actual practice
B. Treat it as a system failure requiring correction regardless of the absence of incidents — normalised deviation from a hard time limit is a precursor to failure, not evidence the limit is unnecessary
C. Address it only with the specific Chief Officers involved, with no wider system review
D. Treat it as acceptable practical flexibility, since no incidents have occurred as a result
Sign in or create a free account to see the answer and explanation.
A. There is no fixed maximum — it depends entirely on the job
B. 48 hours, renewable once without re-inspection
C. 7 days, matching the standard watch rotation
D. 24 hours from issue, with any shorter job-specific time limits also stated on the permit
Sign in or create a free account to see the answer and explanation.
A. Check elapsed time against the 24-hour limit, recognise it's close to expiry, and flag to the authorising officer that revalidation will be needed rather than letting it lapse unnoticed
B. Cancel the job immediately without consulting the authorising officer
C. Wait until the 24-hour mark is actually reached before mentioning anything
D. Accept the outgoing OOW's assessment and take no further action since the job scope hasn't changed
Sign in or create a free account to see the answer and explanation.