Maritime Questions › DP — Blackout Response
G2 trips. Only G3 remains online. G3 alone cannot power all thrusters at current demand. The vessel is 80m from the gas platform. Position has not yet moved but the DP system is reducing thruster power automatically as G3 struggles with load. What is the single most critical action the DPO must take RIGHT NOW?
A. Attempt to manually restart G1 from the bridge engine controls
B. Increase thrust demand to correct the developing position error before it grows
C. Immediately alert the gas platform via radio that the vessel has lost main power and may lose position
D. Switch the DP system to joystick mode to maintain manual position control with the available thrusters
Sign in or create a free account to see the answer and explanation.
A. Wait to see if G1 auto-restarts before taking any action — it may recover within 30 seconds
B. Inform the engine room and wait for their assessment before taking any DP action
C. Close the bus tie immediately to ensure power continuity for all thrusters
D. Immediately check the power status panel to confirm which generators are online, verify the bus is still open, and assess whether the remaining power configuration still meets DP2 WCF requirements in the current conditions
Sign in or create a free account to see the answer and explanation.
A. Switch all thrusters to minimum power to reduce electrical demand instantly
B. Manually close the bus to share the load between both sections and prevent G2 from tripping
C. Wait for the PMS to complete its auto-load-shed cycle before intervening
D. Inform the master immediately, declare a DP Alert, begin controlled manual thruster reduction on the most loaded thrusters to reduce electrical demand and help stabilise G2, while simultaneously monitoring position
Sign in or create a free account to see the answer and explanation.
+7 more DP — Blackout Response questions available
Create a free account to practise all 10 questions, track your accuracy, and build your Reputation Score.
Create Free Account