If a single job (e.g. repairing a radar scanner on the main mast) requires working aloft, electrical isolation, and lock-out/tag-out, what is the correct approach to managing the multiple permits involved?
A. Combine all hazards into a single generic permit with no specific detail
B. Issue only the working aloft permit, since it's the primary hazard
C. Skip permits entirely if the job is considered routine maintenance
D. Issue each relevant permit (e.g. working aloft, electrical/high voltage, isolation lock-out/tag-out) and maintain a master log tracking the status of all permits until the task is fully complete
Sign in or create a free account to see the answer and explanation.
A. Only inspect the kit after the next incident occurs
B. Suspend height work activities until the rescue kit is inspected, confirmed serviceable, and the rescue team has practised with it
C. Use a completely different, unlisted method if the kit looks old
D. Proceed as normal since the kit is listed on the permit
Sign in or create a free account to see the answer and explanation.
A. The bridge does not need to be informed during a rescue
B. This is acceptable as long as the SRL-R operation takes priority
C. Nothing - one competent person is sufficient for any rescue
D. The plan has a single point of failure in personnel; rescue plans should identify enough trained people to cover simultaneous rescue actions and communications, not rely on one person for both
Sign in or create a free account to see the answer and explanation.