After completing overside hull painting, the crew climbs back aboard and immediately moves on to their next task without informing anyone that the job is finished. Two hours later, another officer assumes the area is still an active overside work zone and keeps the exclusion barriers and lifebuoy watch in place unnecessarily. What process failure does this illustrate?
A. No failure - leaving the barriers up longer is always the safer option
B. This is a normal and acceptable outcome of the permit system
C. The crew should have removed the barriers themselves without telling anyone
D. The permit was not formally closed and the authorising officer was not notified of completion, so the system had no way of knowing the hazard had ended
Sign in or create a free account to see the answer and explanation.
A. Only the vessel's general safety policy, with no task-specific assessment
B. A specific risk assessment (or an existing one reviewed and adapted for the task) covering the hazards involved
C. Nothing - the permit form itself is sufficient on its own
D. Only a verbal agreement between the worker and supervisor
Sign in or create a free account to see the answer and explanation.
A. The Master
B. Whichever crew member raised the original request
C. The shore-based office, with no shipboard accountability
D. The most junior officer on watch at the time
Sign in or create a free account to see the answer and explanation.
+5 more Working Height Ptw questions available
Create a free account to practise all 8 questions, track your accuracy, and build your Reputation Score.