The monthly rope inspection record for a headline says "satisfactory". You find external abrasion where it leads through the fairlead. What do you do?
A. Leave it: the last inspection was satisfactory.
B. Fit a sleeve and carry on.
C. Compare the rope with the company's written retirement criteria, and withdraw or crop it if it does not meet them.
D. Use it only as a stern line.
Sign in or create a free account to see the answer and explanation.
A. Nothing — a test lift can proceed immediately after repairs
B. The area within the grab's swing radius should be cleared of personnel before the lift
C. Testing should wait until cargo operations begin
D. Only the crane operator needs to be aware the lift is happening
Sign in or create a free account to see the answer and explanation.
A. Only the weather forecast for the next watch
B. The lunch schedule for the deck team
C. Who must remain clear of the exclusion zone while the lift takes place
D. The cargo manifest for the next port
Sign in or create a free account to see the answer and explanation.
+1682 more Safety & Emergency questions available
Create a free account to practise all 1685 questions, track your accuracy, and build your Reputation Score.
Create Free Account