A permit to work authorises testing a repaired passenger lift from inside the car. Partway through, the technician decides to enter the shaft from another deck to inspect the top of the car. What should happen?

A. Continue; the work is still on the same lift
B. Stop. The task has moved beyond the authorised scope, so the permit must be re-assessed, amended or reissued before anyone enters the shaft
C. Carry on provided the technician tells a colleague
D. Ask the lift manufacturer by email first
Sign in or create a free account to see the answer and explanation.
You're asked to test a deck crane grab after electrical repairs nearby. As the grab is hoisted, what should have happened first?
A. Nothing — a test lift can proceed immediately after repairs
B. The area within the grab's swing radius should be cleared of personnel before the lift
C. Testing should wait until cargo operations begin
D. Only the crane operator needs to be aware the lift is happening
Sign in or create a free account to see the answer and explanation.
A toolbox talk held before a lifting operation should explicitly cover which of the following?
A. Only the weather forecast for the next watch
B. The lunch schedule for the deck team
C. Who must remain clear of the exclusion zone while the lift takes place
D. The cargo manifest for the next port
Sign in or create a free account to see the answer and explanation.
+1497 more Safety & Emergency questions available

Create a free account to practise all 1500 questions, track your accuracy, and build your Reputation Score.

Create Free Account