A Master, justifying a decision to skip a costly and time-consuming control measure identified in a risk assessment, argues that implementing it wasn't 'practicable' given the time available in port. Is time pressure alone a sufficient legal basis for this kind of decision under UK law's 'reasonably practicable' standard?
A. Reasonably practicable is a purely subjective standard, decided entirely by the Master's own judgement at the time
B. Not necessarily — the long-established legal test (from Edwards v National Coal Board) weighs the risk against the sacrifice (in money, time, or trouble) required to avert it, and requires the sacrifice to be grossly disproportionate to the risk before it can be reasonably omitted; ordinary schedule inconvenience is unlikely to meet that bar for a significant risk
C. Yes — any genuine time constraint automatically satisfies the reasonably practicable test, regardless of the severity of the risk involved
D. The reasonably practicable standard does not apply to time-based commercial pressures, only to financial cost
Sign in or create a free account to see the answer and explanation.
A. Daily, weekly, monthly, and annual risk assessments, based purely on time interval
B. Low, medium, high, and critical risk assessments, based only on severity rating
C. Generic risk assessments (company-level), task-based risk assessments (onboard, specific to the job), toolbox talks (discussing the assessment with those doing the work), and personal/dynamic assessment (an individual's ongoing informal check while working)
D. Deck, engine, catering, and bridge risk assessments, based on department
Sign in or create a free account to see the answer and explanation.
A. Nothing further — the generic company risk assessment for enclosed space entry already covers this job
B. Only a toolbox talk is needed, since the team already knows the general hazards of enclosed spaces
C. A new generic risk assessment must be drafted and submitted to the company before this job can proceed
D. A task-based risk assessment specific to this entry and these personnel, followed by a toolbox talk walking the team through its findings before work begins
Sign in or create a free account to see the answer and explanation.
+40 more Risk Assessment Mcq Full questions available
Create a free account to practise all 43 questions, track your accuracy, and build your Reputation Score.
Create Free Account