Auditing the ship's safety records, the Master finds that task-based risk assessments are being completed and filed correctly, but there is no evidence toolbox talks are actually happening before non-routine high-risk jobs — no records, and crew interviews suggest assessments are rarely discussed as a group. What does this indicate, and what should the Master do?
A. It is not a significant concern provided the TBRA documents themselves are accurate and complete
B. It indicates the four-level process has broken down at the communication stage — the TBRA may be technically correct but isn't being shared with or understood by the people actually doing the work; the Master should reinforce that toolbox talks are mandatory before qualifying jobs and verify this through spot checks, not just paper review
C. It indicates the TBRA process itself should be simplified to remove the need for toolbox talks
D. It should be addressed only if an incident has occurred as a result of the missing toolbox talks
Sign in or create a free account to see the answer and explanation.
A. Daily, weekly, monthly, and annual risk assessments, based purely on time interval
B. Low, medium, high, and critical risk assessments, based only on severity rating
C. Generic risk assessments (company-level), task-based risk assessments (onboard, specific to the job), toolbox talks (discussing the assessment with those doing the work), and personal/dynamic assessment (an individual's ongoing informal check while working)
D. Deck, engine, catering, and bridge risk assessments, based on department
Sign in or create a free account to see the answer and explanation.
A. Nothing further — the generic company risk assessment for enclosed space entry already covers this job
B. Only a toolbox talk is needed, since the team already knows the general hazards of enclosed spaces
C. A new generic risk assessment must be drafted and submitted to the company before this job can proceed
D. A task-based risk assessment specific to this entry and these personnel, followed by a toolbox talk walking the team through its findings before work begins
Sign in or create a free account to see the answer and explanation.
+40 more Risk Assessment Mcq Full questions available
Create a free account to practise all 43 questions, track your accuracy, and build your Reputation Score.
Create Free Account