Maritime QuestionsDP — What-If (DPO)

Before commencing a DP2 subsea inspection task, you review the project seabed clearance chart. In current conditions (1.8m swell from NW, 22 knots), your vessel's expected DP footprint extends approximately 12m north of the nominal station position. The seabed exclusion zone for a subsea pipeline starts 9m north. What must happen before you can commence the task?

A. The 3m overlap is within GPS accuracy tolerance and operations can proceed with heightened monitoring
B. Advise the project team of the overlap but let them decide whether to proceed
C. Proceed if the ASOG yellow alert has not been triggered — the ASOG limit is the binding constraint, not the footprint
D. Operations cannot commence until either: the station position is adjusted to create adequate clearance in all weather directions, or the conditions improve to reduce the footprint, or a heading change is agreed that shifts the footprint away from the exclusion zone — and this must be confirmed with the project team. A footprint overlap is not an operational risk to accept by monitoring more closely
Sign in or create a free account to see the answer and explanation.
You're on DP2 watch during a cable survey operation. The ROV pilot requests you shut down the port aft azimuth thruster because its cavitation noise is interfering with the multibeam sonar. The thruster is currently not contributing significant thrust in the prevailing conditions. You shut it down. What critical DP risk has this action introduced?
A. A single thruster shutdown is permitted at any time without reassessment on a DP2 vessel
B. None — if the thruster was not contributing thrust, it was not part of the redundancy calculation
C. The risk is limited to reduced manoeuvrability in manual mode only
D. Shutting down a thruster changes the Worst Case Failure and may remove the vessel from DP2 compliance — the remaining thruster configuration must now be consequence-tested to confirm DP2 capability is maintained, and the ASOG status must be reassessed before operations continue
Sign in or create a free account to see the answer and explanation.
During a DP2 anchored-spread mooring operation, your two DGNSS systems begin showing positions that diverge by 4.2 metres and are moving further apart. The Fanbeam is not available at this worksite. Both DGNSS units show normal signal strength and differential correction status. What is your immediate decision process?
A. With two diverging DGNSS units and no third reference, you cannot determine which is correct. Immediately inform the master, assess whether operations can safely continue with degraded reference confidence, and consider whether an additional reference source (taut wire, radar range/bearing, another DGNSS unit) can be deployed or activated before the divergence worsens
B. Accept the average of the two positions as the reference and continue operations
C. Accept whichever unit was installed more recently as it is likely more accurate
D. Continue operations — a 4.2m divergence is within normal GPS accuracy tolerance
Sign in or create a free account to see the answer and explanation.
+6 more DP — What-If (DPO) questions available

Create a free account to practise all 9 questions, track your accuracy, and build your Reputation Score.