A DP2 offshore crane vessel has two wind sensors fitted on the mast. During operations, one wind sensor fails and returns zero wind speed and direction. The DPO is aware the remaining sensor is reading 22 knots from the SW. How does the DP system use wind sensor data, and what is the consequence of accepting a failed zero-reading sensor?
A. Wind sensors are advisory only — the DP system does not use wind data directly and there is no consequence to a failed sensor
B. The DP system averages both wind sensors, so a failed zero-reading sensor will halve the displayed wind speed but the DP force calculation remains accurate
C. Wind sensors are only used during auto-heading mode and have no effect on DP position control
D. The DP system uses wind sensor data as a feedforward input to anticipate and pre-compensate for wind forces before they create a position error — a sensor reporting zero wind will cause the DP system to under-compensate for actual wind load, potentially leading to position excursion before the position error loop corrects
Sign in or create a free account to see the answer and explanation.
A. The vessel can maintain position after any failure, including fire or flooding in a single compartment
B. No guarantee of position holding — DP Class 2 only requires a backup mode to be available
C. The vessel can maintain position after a single failure of any active component or system, provided redundant systems are in place and operational
D. The vessel can maintain position only if the failure occurs in an external reference system
Sign in or create a free account to see the answer and explanation.
A. DP3 requires redundant systems to be located in separate watertight compartments with physical separation, such that a single fire or flood cannot affect both systems simultaneously
B. DP3 requires full redundancy in all active components, identical to DP2 but with an additional manual backup mode
C. DP3 applies only to semi-submersibles and is not relevant to monohull vessels
D. DP3 requires three independent DP control systems operating in parallel at all times
Sign in or create a free account to see the answer and explanation.
+17 more DP — Fundamentals questions available
Create a free account to practise all 20 questions, track your accuracy, and build your Reputation Score.
Create Free Account