Maritime QuestionsDP — Crane Operations

During an ROV component deck-to-water deployment, the client requests the DPO hold position within ±0.2m tolerance so the ROV umbilical doesn't foul. The current ASOG is set for ±1.5m tolerance in the prevailing weather. What should the DPO do?

A. Agree but log that the deviation from ASOG was at the client's request, which transfers liability
B. Explain that ±0.2m is not achievable in current conditions without exceeding ASOG limits; the position tolerance in the ASOG reflects what the vessel can reliably maintain in the current weather — operating to a client-specified tolerance that is tighter than the ASOG allows is not safe and should be refused until conditions allow or the operation is redesigned
C. Agree to the ±0.2m tolerance and attempt to hold it — the client knows the operational requirements best
D. Reduce the ASOG limits temporarily to match the client's requirement
Sign in or create a free account to see the answer and explanation.
How does a heavy crane lift affect the DP system's position-keeping model and why does this matter?
A. Crane lifts only matter for DP if the load exceeds the vessel's Safe Working Load
B. Lifting a heavy load shifts the vessel's centre of gravity upward and athwartships (depending on crane position), altering the vessel's roll and pitch characteristics and therefore the environmental force response — a DP system not updated with the correct crane position and load may miscalculate the forces needed to maintain position, reducing accuracy
C. Crane lifts have no effect on the DP model — only weather forces are modelled
D. The DP system automatically compensates for crane loads through the load cell feedback
Sign in or create a free account to see the answer and explanation.
What is load pendulation and why does it create a risk for DP position-keeping?
A. Pendulation is the rotation of the crane jib, not the load
B. Pendulation has no effect on DP — it is a rigging safety concern only
C. Load pendulation is the swinging of a suspended load in an arc below the crane hook, which creates a dynamic, oscillating side force transmitted through the crane structure to the vessel hull — the DP system must counter this cyclic force, and the constant changing direction of the force can cause oscillating thruster demands that stress both the DP system and the power management system
D. Pendulation only occurs when the load is in the water, not when suspended in air
Sign in or create a free account to see the answer and explanation.
+6 more DP — Crane Operations questions available