Bridge Errors: The Passage Plan Nobody Checked

🕑 5 min read words Safety • Incident

Error type: Passage plan, waypoint and chart not checked; ECDIS alarms and safety settings not used
Cases compared: Caledonian Sky (2017), Ou Ya Leng 6 (2019), Meshka (2025), Quest (2007)
Use it for: MCA orals (passage planning, ECDIS, chart reliability, parallel indexing), appraisal and execution of a plan
Sources: BMA report (Caledonian Sky); RMI Maritime Administrator report (Ou Ya Leng 6); SHK 2026:10e (Meshka); BMA and DMAIB joint report (Quest)

CATZOC D the data-quality rating of the only chart Caledonian Sky used9 NM between the last waypoint of Ou Ya Leng 6 and the atoll, where the plan simply stopped3 m water under a bulk carrier drawing 7 m, on a first transit of the Øresund

The Plan Was On the Screen. Nobody Asked What Was Behind It.

IMO Resolution A.893(21) sets out four stages of voyage planning: appraisal, planning, execution and monitoring. The four ships here all had a plan. What they lacked was an honest appraisal of it, or a way to monitor it as the ship went.

In each case the sensors worked. The ECDIS or ECS was running, the radar was on, the GPS was good. The errors were human: a route accepted because it had been used before, a plan that ended before the danger, a missing chart cell, a decision to leave the plan for the scenery.

The Cases

Caledonian Sky, Raja Ampat, 4 March 2017

An expedition cruise ship with 102 passengers and 79 crew made a six-mile passage between anchorages. The route was the track used on a cruise in November 2016 under a different Master. At 1241 she ran aground on an uncharted reef at about 8.8 knots. Nobody was hurt, and she was refloated about ten hours later.

  • What the bridge team did: The Master accepted the track and asked the Navigator twice why the route was laid that way; both times the answer was that this was the route used before. The only chart was an ENC with a data-quality rating of CATZOC D. The ship ran at about 9 knots against a planned 6, and a man overboard drill was run in confined water.
  • The specific error: Treating ‘we did it before’ as a risk assessment. The Admiralty chart of the area, which was not on board, showed a larger drying area and did not show the channel the track used. The Sailing Directions were not consulted. The ECDIS replay showed not one fix or line of position, and the safety contour of 5 m allowed nothing for squat.
  • The barrier that would have caught it: A second chart and the Sailing Directions at the appraisal stage, a safety contour set from draught, squat and tide, fixes and a parallel index, and a weak answer to ‘why this route?’ treated as a reason to stop.

Full case: Caledonian Sky: ‘this is what we did before’.

Ou Ya Leng 6, Taka Atoll, 2 January 2019

A 94 m refrigerated fish carrier was steering 115° at just over 10 knots towards a fleet rendezvous when she ran onto the reef at Taka Atoll at about 2306. All 24 crew survived. The ship was lost and some 155-160 tonnes of fuel oil leaked onto the reef.

  • What the bridge team did: The Master plotted six waypoints. The last was about 9 NM from the atoll and the plan simply stopped there, with no clearance distance and no instruction to check position. The Night Orders said to call the Master at 2200. The Third Officer, absorbed in the weather, forgot. At about 2230 he saw something ahead that might have been land, and did not look at the chart system or either radar.
  • The specific error: A plan with no end. The only chart system was an ECS rated for coastal waters, loaded with a low-quality leisure-grade chart, and neither the route-departure alarm nor the waypoint alarm had been set up. Equipment was working. It was not used.
  • The barrier that would have caught it: A plan that runs to the destination with a no-go line, the chart alarms switched on, a Night Order that triggers a call, and a glance at the screen when something looks like land. A glance at the position would have given time to alter or call the Master.

Full case: Ou Ya Leng 6: the Taka Atoll chart trap.

Meshka, Øresund, 31 May 2025

The bulk carrier Meshka, in ballast and southbound on passage from Tarragona to Vysotsk, was making her first transit of the Øresund. The Swedish traffic centre saw her drifting outside the lane and warned her. She grounded off Landskrona in 3 m of water on a draught of 7 m. She was refloated on 7 June with no substantial damage and no pollution.

  • What the bridge team did: The bridge team continued with an ECDIS that lacked detailed chart cells for the Øresund, and nobody caught the gap during planning or chart ordering. As the ship drifted off the lane, no one on the bridge noticed in time.
  • The specific error: SHK found inadequate voyage planning, insufficient crew knowledge of ECDIS limitations, poor adherence to navigation procedures and deficient bridge teamwork. The chain began in the office, with how the charts were ordered.
  • The barrier that would have caught it: Checking chart coverage for the whole passage before sailing, especially before a first transit of a narrow strait, plus a working cross-track limit and a monitoring routine. The ship-reporting system did warn her but too late.

Full case: Meshka: ECDIS and voyage planning in the Øresund.

Quest, Disko Bay, 27 June 2007

A 45.6 m expedition ship with 54 passengers and 20 crew, newly re-registered with a new crew, was running close to icebergs and the coast at about 9 knots to show passengers the scenery. At 0648 she hit an uncharted rock 0.24 miles from the shore. Nobody was hurt.